Bid Title:
The Johns Hopkins Hospital - Meyer Renovation Project
Bid Due Date:
12/4/14
Bid Due Date Time:
2:00 PM
Project Description:
The work of this Project includes the following: The Meyer building is a 32-year old, 12-story building constructed in the early 1980’s located on the Johns Hopkins Hospital’s East Baltimore Campus. The 12-stories include a basement (B) and sub-basement (SB) below grade, a penthouse (PH) mechanical space at the 9th floor, and elevator machine rooms at the 10th floor. The building consists of two (2) wings; the patient wing and the lab wing. The renovations will incorporate interior renovations to three (3) inpatient units on floors 7, 8, and 9 and associated support space; interior upgrades to the 1st floor public corridors; building infrastructure
upgrades including majority of MEP systems serving the entire building both in the 9th floor penthouse, the SB mechanical/electrical (MEP) space and the MEP shafts; replacement of the concrete floor slab in a portion of the SB; construction of a new low voltage IT shaft on the east face of the building exterior; waterproofing of the Meyer Courtyard adjacent to the west side of
the building; and modifications to the east face of the building along Wolfe Street at the 1st floor level. Floors 3 through 6 house active inpatient units and floors B through 6 house a number of active lab spaces. Floors SB through 8 also contain numerous active outpatient operations and physician offices. All areas noted as active will remain occupied throughout the renovation
process and hospital functions on these floors must be maintained.
upgrades including majority of MEP systems serving the entire building both in the 9th floor penthouse, the SB mechanical/electrical (MEP) space and the MEP shafts; replacement of the concrete floor slab in a portion of the SB; construction of a new low voltage IT shaft on the east face of the building exterior; waterproofing of the Meyer Courtyard adjacent to the west side of
the building; and modifications to the east face of the building along Wolfe Street at the 1st floor level. Floors 3 through 6 house active inpatient units and floors B through 6 house a number of active lab spaces. Floors SB through 8 also contain numerous active outpatient operations and physician offices. All areas noted as active will remain occupied throughout the renovation
process and hospital functions on these floors must be maintained.
Posted On:
2014-11-18 13:07:35
Notes:
Questions to Whiting-Turner are due no later than November 25, 2014 at 10 am.
Contact Information
Name:
Jack Streett, Project Manager
Phone Number:
410-494-7449
Email Address:
Jack.Streett@whiting-turner.com