The Silver Spring Artspace Project includes both a renovation of an existing commercial building for future use and new construction of a five (5) story residential building (Lofts), consists of one (1) level parking garage with four (4) stories of wood framed residential units above.
Important dates:
- Bids due back: July 31, 2019
- Anticipated Award: August 30, 2019
- Anticipated NTP from Owner: June of 2019
- Mobilization/start of site work: July of 2019
- Schedule duration of project: 16 months
The Bid Plan Documents will be sent via email to interested bidders via a web link for download.
-
Plumbing
-
Masonry
-
Finish Carpentry
-
Waterproofing
-
Insulation
-
Doors, Frames, Hardware
-
Drywall
-
Paint
-
Tile
-
Flooring
-
Appliances
-
Cabinets
-
Site Concrete (sidewalks)
-
Landscape